Wolfgram Bank Stablization Project

Status Complete:

Description Of Project

Wolfgram Bank Stablization Project, Lake Forest; restabilize an 86 foot lineal stretch of the west bank of the ditch which has been badly eroded by natural forces. Consisted of vegetation removal, limestone pieces placement, eearthwork and grading, native revegetation, and placement of erosion/sediment control.

Detailed Status

Preliminary Planning Phase Completed?
Discussed Project
Directed To Proceed
Survey Started
Survey Completed
Environmental Study Started
Environmental Study Completed
Survey Platted
Initial Planning Started
   
Permitting And Approval Phase  
Initial Planning Completed
Applied for Grant Monies
Submitted Plans To District
Submitted Plans To SMC
Submitted Plans To Other Agencies
Revision of Plans To Satisfy Agencies
Submitting Plans To Secure Permits Started
Securing Of Permits Completed
   
Construction Stage  
Starting Taking Bids
Completed Taking Bids
Awarded Contract
Preconstuction Meeting
Started Construction
Started Observation Of Construction
Completed Construction
Final Inspection of Construction
Secured Grant Monies
   
Maintenance Stage  
Started Maintaining Construction
Maintaining Construction